Skip to content
Tab thru menu links. Enter key for site map

SRC 3rd Floor Renovation Details

SRC 3rd Floor Renovation

UREC is excited to announce an update for the flooring in our 3rd floor auxiliary gym space!  We will be replacing the entire flooring system. The project timeline includes:

  • Monday, April 28th removal of the dasher board system on court 2
  • Friday, May 2nd courts 2 and 3 will be closed 
  • Tuesday, May 6th full closure of the 3rd floor

We will move some of the cardio equipment to the track area during this closure.  

We anticipate having the space open by Tuesday May 27th. Continue to check our website for any updates.

Thank you for your patience and understanding during this project.  We look forward to the improvements in this space to better serve your fitness and recreational programming opportunities!

- The UREC Team


Expected Updates